Reopening of the Zwergenschloss nursery

After almost a year of renovation work, the “Zwergenschloss” nursery in the Herzfelde district will reopen its doors on 19 October 2026. This marks the return of everyday nursery life to the historic building.

Over the past few months, specialist contractors, various trades and the relevant departments of the municipality of Rüdersdorf near Berlin have worked together to carry out extensive refurbishment work. The aim was to ensure the long-term preservation of the building’s structure and to create a modern and attractive environment for the children and teaching staff.

The nursery’s equipment has also been updated. Furniture, as well as play and craft materials, that were outdated or worn out have been replaced. The nursery team were involved in selecting the new equipment and were able to contribute their own wishes and ideas.

Before the children move back in on 19 October, the refurbished ‘Zwergenschloss’ will be officially opened on 16 October 2026 from 5.00 pm to 6.30 pm. Together with the children, parents, the specialist contractors involved and the nursery’s support association, there will be a celebration on the nursery grounds, followed by a tour of the refurbished premises.

Members of the press are also warmly invited to come along and see the completed work for themselves.

Background:

The Zwergenschloss nursery in the Herzfelde district had been closed since October 2025 due to extensive refurbishment work. Due to rising damp – exacerbated, amongst other things, by a burst water pipe last autumn – work was initially carried out from late 2025 to early 2026 to dry out the interior walls. To this end, a horizontal damp-proof course was installed all round the walls in contact with the ground using an injection method. This involved drilling small holes at intervals of 10–15 cm into the damp masonry and injecting a silicate resin, which blocks the fine channels in the stone and thus stops the rising damp. This required all walls in contact with the ground to be stripped back from the inside. As part of this, plaster, tiles and wallpaper were extensively removed.

Once the horizontal damp-proof course had been installed and a lengthy drying-out period had taken place, the interior walls could be replastered from scratch and repainted. To begin with, a sealing slurry was applied to the previously treated walls, which were then replastered. The wet rooms and laundry rooms on the ground floor were also included in the refurbishment. The old tiled splashback was completely removed and replaced with easy-to-clean HPL panels. The sanitary facilities were renewed and the laundry room refurbished. As the refurbishment progressed, work continued on refurbishing the stairwell, the windows and window reveals within it, the entire basement area beneath the kitchen, and the repair of the retaining wall supporting the internal emergency staircase.

Extensive refurbishment work was also carried out on the first and second floors. Trades such as heating and plumbing, flooring and painting were involved. The wallpaper, walls, doors, floors and the stairwell were all refurbished.

A large number of items, such as furniture and play and craft materials, were disposed of whilst the drainage works were underway, due to their age, condition and the fact that they were no longer suitable for educational purposes.

New, modern and attractive furnishings were ordered and have since been delivered and fitted.

Only a few minor measures and some finishing work remain to be done, but these will not prevent the move from going ahead.