Fundamental expansion of the K 6420 - current status

From Monday, 14 April 2014, work will begin on the 3rd construction phase in Hans-Striegelski-Straße, from Schulstraße to the Alte Post.

 

This section will be fully closed for this purpose. The diversion traffic out of town in the direction of the BAB 10 motorway will then turn right from the Kalkgrabenbrücke bridge via Schulstraße and Straße der Jugend to the Alte Post, where it will return to the already completed construction section of Straße der Jugend.

 

There will be a parking and stopping ban in Schulstraße during this time to allow bus traffic to pass unhindered.

Road users are asked to pay attention to the two-way crossing with the tram.

 

In the other direction of travel, the existing diversion arrangements will remain in place.


In the first construction phase (Dr. Külz-Straße to Landhof), the right-hand carriageway is to be asphalted (except for the surface course) by the end of April so that traffic can then be switched to this lane and the construction work can be carried out on the left-hand side of the carriageway.


 

All construction work is currently on schedule.

 

 

Source photo: © Andreas Morlok / PIXELIO