Full closure in Karl-Liebknecht-Straße between Potsdamer Platz and Woltersdorfer Straße - date still open

The latest issue of *Stienitz Aktuell* announced a full closure of Karl-Liebknecht-Straße from 1 November 2021. Unfortunately, this report has since been overtaken by events, as we have not yet received approval for the amended construction site traffic lights from the district’s road traffic authority. A partial closure (during the day, whilst work is in progress) will therefore begin on 8 November 2021 at the earliest.

As soon as the final date has been confirmed, we will provide detailed information about the planned measures. We plan to publish information on our website, in the press and via a leaflet sent by post to all immediate neighbours.

Civil engineering works between Potsdamer Platz and the Woltersdorfer Straße junction have been on hold for some time now. This is because the external safety coordinator has prohibited construction work in this area whilst traffic is flowing. As a local authority, we have no influence over this assessment. Due to the necessary pipework, the excavator has to dig down to a depth of up to 4 metres, which is why it is not possible to use smaller machinery. The large excavator required, in turn, has such a wide swing radius that access from this side has been prohibited.

For this reason, the municipality of Rüdersdorf near Berlin has examined a number of measures (see below). Having weighed up all the options, Karl-Liebknecht-Straße between Woltersdorfer Straße and Potsdamer Platz will be partially closed to traffic. The full closure is expected to take place on weekdays during the construction work, from 7.00 am to 5.00 pm. At other times, the road will be open to traffic under traffic light control. One side of the footpath will remain accessible. The construction company is bringing in additional workers to the site.

Fire brigades and emergency services can pass through the building site at ANY TIME. Solutions for the adjacent roads are currently being finalised in consultation with the waste management companies.

The exact date of the partial road closure has NOT YET been confirmed.

Before the partial road closure comes into effect, Friedenstraße will be levelled; in other words, the gravel road will be graded to make it more passable. As there will then be no through traffic from the GO petrol station bypassing the roadworks, this measure will not cause an intolerable burden for residents of Friedenstraße.
We have examined the following measures in advance to avoid the closure:

  • Reducing the construction time by building 7 days a week and 24 hours a day: not possible, as this would require going through a lengthy, separate environmental impact assessment approval process.
  • Alternative method: Not possible due to the depth of the excavation pit.
  • Construction of an access road across the Altenaer Acker: at least three plots of land are not owned by the local authority. Regardless of the topographical and technical feasibility, a construction access road would have had to be built – subject to contractual agreements with the owners – and subsequently dismantled. This would require a planning and approval process. The effort, time, costs and benefits involved are completely out of proportion.
  • An expert was consulted to assess whether the large lime trees would survive the forthcoming construction work. In the event that the trees were to be too severely affected by the building works and would not survive, early felling was also considered. This would have allowed for greater freedom of movement on site. However, the expert report concluded that the trees have a good chance of survival.


On behalf of the municipality of Rüdersdorf near Berlin, I would like to apologise for any inconvenience caused by the construction work and thank you for your understanding.

Sabine Löser
Mayor