Press release from “Die Autobahn GmbH des Bundes”:
Hohen Neuendorf, 7 September 2022: Since June, construction work has been underway to completely replace the concrete carriageway with an asphalt surface on the carriageway heading towards the Spreeau motorway junction, as well as to resurface the existing asphalt surface across the entire width of the carriageway heading towards the Barnim motorway junction. The asphalt surface layers on the slip roads at the Rüdersdorf junction are also being renewed as part of this maintenance project.
The construction work is being carried out using a ‘half-side’ method with a 3+1 traffic management scheme, i.e., there are two lanes in each direction – on the carriageway where work is currently taking place, one lane is available, whilst the second is routed in the opposite direction on the other carriageway.
The resurfacing work on the carriageway heading towards the Barnim junction has now been completed. Since the start of this week, the new asphalt structure (base and binder courses) has been laid on the second and third lanes of the carriageway heading towards the Spreeau junction. At the same time, work is underway to install the drainage systems on the central reservation, as well as preparations for the installation of the necessary vehicle restraint systems (concrete safety barriers).
The installation of the mastic asphalt surface course is scheduled for the end of September. To complete the project, work will then be carried out to construct the concrete safety barriers and apply road markings.
The reorganisation of traffic flow for the subsequent and final construction phase – involving the laying of the new asphalt surface on the first carriageway and the hard shoulder – is scheduled to take place from 6 October 2022. In addition to the deceleration lane at the Rüdersdorf junction exit, the asphalt surface layers on the ramps leading from the Rüdersdorf junction to the junction with the L302 will also be resurfaced. In this context, the Rüdersdorf junction will be completely closed for approximately 7 weeks in October/November; further information on this will be provided separately in due course.
To ensure the necessary clearance for construction work at the L302 junction, traffic travelling from Rüdersdorf to Schöneiche and from Schöneiche to Rüdersdorf will need to be managed using mobile traffic lights, with half the traffic flowing in one direction and the other half in the opposite direction, for approximately one week (expected to be in early November 2022).
We ask for your understanding and cooperation, and would ask you to be particularly vigilant. Please be aware that disruption is likely.