Restrictions on the Mühlenfließ bridge on the A10 motorway

Due to the ongoing repair work on the Mühlenfließbrücke bridge and the cramped conditions, there will be unavoidable restrictions over the next few weeks. Autobahn GmbH des Bundes reports that cutting work will take place from 13 April 2026, followed by milling work on the road surface from 20 April. This is preparatory work for the renewal of the carriageway surface. The mastic asphalt will be laid on 23 April.

During the entire 17th week (20-26 April), traffic will only be able to use one lane along the entire length of the bridge due to the construction work and the required safety distances.

In week 16 (13-19 April), two-lane traffic is guaranteed.